Thursday, 16 February 2012

House & Shed now attached to tank

Things are moving along. Today, John (builder) came and put a support beam in the wall between the kitchen and bathroom. We are pretty sure it's not a load bearing wall, but would rather be sure than sorry. Don't want the roof caving in! He also took out a window. Robert now has the internal walls to construct - to turn the big space into a "laundry-in-a-cupboard", a bank of storage cupboards, a toilet, and a bathroom with sliding door.


Whilst they were working inside, Pete (plumber) was working outside, connecting the house and shed to the tank with PVC piping, using all those lovely trenches Robert dug!